PDF page 246
229
POST-WAR ELECTRIC POWER DEVELOPMENT
to this because it is necessary you should know what has happened
in the interval and also to show that the Government of India has
been pursuing the matter in all earnestness and with all speed.
The Triple Programme
There is another important development in electrical policy to
which I would like to draw the attention of all of you here. You
will recall that at the last meeting of the Policy Committee,
Mr. Collins, on behalf of the Bombay Government, made certain
references to the contemplated introduction of the “Grid” system
in the Bombay Presidency. During the last year, we in the
Government of India have given a great deal of thought to the
regional as distinguished from the local development of electricity
in different parts of this country. We have felt more and more
that if the services offered by electricity are to be brought to
the door of producers as well as the consumers at the cheapest
possible rates compatible with efficiency, we may have to follow
albeit cautiously and gradually, the triple programme on which
the Central Electricity Board in the U.K. have worked from the
very beginning, viz. :—
(a) The creation of large-scale power stations located in the
main industrial areas under the control of public supply
undertakings ;
(b) the construction of main transmission system (with smaller
secondary lines attached to it for tapping agricultural
and other outlying areas) so that the entire region to be
developed by the main system can be held in a power ring
or a series of power rings radiating out from the large
scale power stations ; and
(c) standardisation of frequency as far as possible within the
region to be developed by the power system.
This triple programme constitutes the foundation of the “Grid”
system, as we know it, to be operating in the U. K. since 1926
and it is my hope that if such a scheme of regional development
is adopted in this country, we may before long bring the great
boon of cheap electricity service to the door of everyone, high
or low.
You may be interested to know that when the “Grid” system on
a large scale was first contemplated in the U. K. it was estimated
that by 1940-41 the national production of electricity would reach the
PDF page 247 (printed page 230)
230 DR. BABASAHEB AMBEDKAR : WRITINGS AND SPEECHES
colossal figure of 25,000 million units and the working cost of
electricity would by that date fall from 9.4d, as recorded in
1925-26, to less than 4d. per unit, while the large industrial
consumer would be able to obtain his power requirements at
½d.
Items On Agenda
I will now turn to the Agenda for our meeting to-day. As
you will see, there are altogether four items on the Agenda.
Item 4 places before you for your consideration two schemes,
one for the Technical Power Board and the other for sending
Indians to foreign countries for training in electricity. Neither
is a controversial subject. I will not therefore take your lime
in dwelling upon them.
Item 2 on the Agenda is unfortunately not quite so
uncontroversial as item 4. Item 2 relates to the question
of applying to electrical undertakings certain accounting
principles for ascertaining their income, expenditure and
profits. This item is not as controversial as it appears. The
issue raised by this item covers two questions and not one,
and the controversy would be very much narrowed if they
were considered separately.
The first question is whether the dividend of an electricity
supply undertaking should or should not be related to the
charges for consumption of electricity. The second question is
how to determine reasonable dividend. On the first question,
I venture to say, there can be very little dispute. Electricity
is to be a prime necessity of the people both for production
and consumption. The price of such a prime necessity cannot
therefore be at the will of the suplier. The whole industrial
future of India will be put in great jeopardy if India could not
ensure cheap and abundant supply of electricity. The necessity
of correlating dividends to charges is therefore paramount. If
this is granted, the necessity of enforcing rules of accounting
which will give the undertaking a reasonable return but no more
and choke all holes for concealed profits cannot be disputed.
Principles Of Accountancy
The issue then becomes a secondary one. In pressing for enunciating
principles of accountancy we are not introducing any revolutionary
idea. We are following the lines laid down in British Legislation on
PDF page 248
231
POST-WAR ELECTRIC POWER DEVELOPMENT
Electricity contained in the London Electricity Act of 1925 and
the Electricity Supply Act of 1926. The Electrical Commissioner
with the Government of India has drawn up a Memorandum
in which he has proposed a set of such accountancy principles
for being applied to electricity undertakings. His Memorandum
was circulated to the Provincial Governments and to Electrical
Undertakings for their opinions. There has been unfortunately
some divergence of opinion. As a means of bridging the gulf,
the Government of India proposes to appoint an Advisory
Board to advise on principles which may be just and proper.
I hope you will regard this solution as a satisfactory one.
There remain items 1 and 3 of the Agenda. They are
indeed the most. important items of our Agenda and you will
bear with me if I take some of your time to deal with them.
With regard to item 1, it might be well to refresh your
memory by telling you how the position stood at the last
meeting of the Policy Committee. At the close of the discussion
of the items on the Agenda the Policy Committee desired that
the Labour Department should draft a Resolution embodying
the measure of agreement reached and that it should be
placed for discussion at a subsequent meeting of the Policy
Committee. A draft Resolution was accordingly drawn up
which is in the following terms :—
“That this meeting recomends that the further development
of electricity supply in India be actively pursued as a State or
quasi-State enterprise and that steps be taken to eradicate any
factors that retard the healthy growth of electrical development
in the Provincial, State or Local authority—owned undertaking
as well as the commercially owned undertakings.”
It was felt that the draft Resolution was not very clear.
The Resolution spoke of further development. It said nothing
about the undertakings that have already come into existence.
The Resolution spoke of the necessity of controlling factors
likely to hamper or retard the healthy growth of electrical
development but did not specify what the factors were. It
was therefore felt desirable that the Resolution should be
again carefully considered in the Policy Committee to clear
up elements of doubts. This is how item 1 comes to be what
it is.
PDF page 249 (printed page 232)
232 DR. BABASAHEB AMBEDKAR : WRITINGS AND SPEECHES
State Control And Ownership
The discussion at the last Policy Committee meeting seemed to
indicate clearly the intention that electrical supply enterprise in
areas where there is none at present should be pursued as a State
or a quasi-State enterprise ; but there remained an element of
doubt as to the extent to which the State should come in those
areas in which electrical undertakings were already functioning.
For instance, is it advisable that the State or other authority
should as a general rule exercise an option to take over an
undertaking whenever under the terms of an individual licence
such option arose ? And is it advisable that the State should
exercise control over existing privately—owned undertakings for
the purpose of securing bulk supply for regional development or
control of generation ? There may be cases in which in order to
secure suitable regional development bulk supply from some other
undertaking should be given to some existing undertaking and
that it may be that the manner in which an existing undertaking
operates and expands may have to be brought into line with
general schemes for regional development. We wish, therefore,
in this discussion to get clarification not only as to the extent to
which State ownership should come in but also as to the extent
to which the State should control where State ownership cannot
immediately become operative.
Jevon’s Economic Criteria
The issue between State enterprise and private enterprise has
ever been a matter of controversy. This controversy is now
resounding in India in full blast since we have started the
project of planned economy. Old Jevons in his tract on State in
relation to Industry, attempted to formulate certain economic
criteria by which the line between State enterprise and private
enterprise can be drawn and which have been the gospel of the
opponents of State enterprise. According to Jevons, there were
four criteria which ear-marked an industry for State ownership.
They were (1) small capital account: (2) routine operations : (3)
the co-ordination of several services such as Posts, Telegraphs
and Telephone and (4) the sufficiency of a single all-embracing
plant as in the case of water and gas supply.
The followers of Jevons in this country propose to add some more
criteria, the object of which is to restrict the field of State enterprise
PDF page 250
233
POST-WAR ELECTRIC POWER DEVELOPMENT
except in one case, viz., they are prepared to enlarge the field
by allowing the State free field in such cases which could not be
profitable for private enterprise to undertake. The controversy
may have had some solid basis when private enterprise was
a fact. But to-day private enterprise is only a phase. There is
nothing private in an economic order when industry is carried
on by huge Public Joint Stock Companies. There is nothing of
individual enterprise in an economic order where the slogan of
a business firm is caution and not adventure and where the
prime consideration is to stabilise profits by seeking to maintain
in an orderly permanence existing economic conditions. It is
unnecessary for me to enter into this controversy. For there are
very few opponents of State ownership and State control who
do not make an exception in the case of electricity.
Item 3 raises the question as to who should exercise the
option when it falls due by reason of the termination of the
licence issued to an electrical undertaking for the supply of
electricity. The matter of purchasing an electrical undertaking.
This question is now regulated by the provisions of Section 7 of
the Indian Electricity Act. According to this section, the authority
to exercise the option to purchase vests in the first place with
a Local Authority and where the Local Authority does not elect
to exercise the option it passes to the Provincial Government.
The question raised by item 3 on the Agenda is whether it is
not desirable that option should also be given to the Central
Government and, if so, at what stage and under what conditions.
It is proposed that the Central Government should also have
an option to purchase. Having regard to the fact that electricity
is a public utility, there ought to be no difficulty in vesting the
Central Government with such an authority.
Provincial Or Central Control ?
Unfortunately, there seems to be some reluctance to accept
this principle. Planning in India has been confronted with
two issues, the issue of State versus Private enterprise and
the issue of Provincial or Central control. With both issues
we are all quite familiar and item 3 deals mainly with the
second issue. To those who believe in State enterprise it should
be a matter of small consideration whether the enterprise
should be Provincial or Central and little or no objection